I have one doubt. Let say my consuming segment con...
# random
s
I have one doubt. Let say my consuming segment configuration is set to to certain values. 1. Size: 300 MB 2. Rows: 500k 3. Time: 24 Hours Then I want to change the rows and bring it down to 100k. So, now I made that change. So will my consuming segment which has consumed more than that number of rows will perform the commit? If yes, it will be after I perform rebalance of servers?
j
Yes these changes will applied for the next set of consuming segments
m
@Sumitra Saksham you are probably better off posting in #C011C9JHN7R
s
Sure @Mayank. Will take care from next time
m
No worries, thank you. Just saying because #C011C9JHN7R is monitored for answering questions, #CDRJ5UE21 may not be
s
Sure @Mayank